In the Kharkiv airport level of work performed is 61%.
Reconstruction of the Kharkiv airport should be completed before the end of the year. The airports of Lviv and Kharkiv - the cities that will host matches for Euro-2012 are actively repairing the runways.
The reconstruction of Kharkiv airport employed 155 people and 112 vehicles. The level of work performed to date is 61%. A complete reconstruction should be at the end of 2011.
The International airport "Lviv" just started to lay concrete at 795 meters of elongated section of the runway.
On the construction of the runway there is installation of form-factor, as well as works on dewatering.
And in Donetsk airport in June they should put the updated runway in operation.