The reconstruction of the Kharkiv airport with the construction of a new runway is 61% made. This Information Centre "Ukraine-2012" was told in the National Agency of Euro 2012 (Ukrevroinfraproekt).
The total volume of construction works on covering the runway is: without the top layer of concrete M400 - 1850 m, including ready covering - 1800 m. 155 people and 112 vehicles work on the facility.
Kharkiv airport began the reconstruction in August 2009 and it will be finished in the IV quarter of 2011.
Information Center "Ukraine-2012"