As of April 20, 48% of works on reconstruction of airfield complex of International Airport "Kharkiv" were done. This was reported in "New Systems AM" (Kharkiv airport operator). Currently 99% of construction works on the platforms were finished. 1,722 m of a new runway without the top layer of concrete M400 are ready, with the top layer of concrete M400 - about 850 m. 86 employees and 39 units of construction machinery are involved in the work. As for the construction of air-traffic control tower, it is now ready to install the piles. 24 workers and 10 units of construction machinery are involved in this work.
Work on the construction of a temporary terminal is going according to schedule. Workers expect the earlier ordered hangar doors from Swedish manufacturer "Megadoor" to arrive at the construction site. Investments are coming timely. For April 20, it has already been allocated nearly UAH 32 mln. of the planned UAH 41.7 mln.