52% of the total work done on the reconstruction of IA Kharkiv airfield. This Information Centre "Ukraine-2012" was told in the National Agency Euro (Ukrevroinfraproekt).
1850 meters without the top layer of concrete M400 were laid on the runway, 1275 meters of which are finished cover. Construction of aprons is 99% done.
155 people and 112 vehicles work on site. Reconstruction of the airport with the construction of a new runway IA Kharkiv began in August 2009 and the object should be put into operation in the IV quarter of 2011.
Information Center "Ukraine-2012"