01 July 2009
Inspection of the Reconstruction Project for Airfield of Kharkiv International Airport is finished
Share news:
Ukrgosstroyekspertiza State Enterprise approved a project of Kharkiv International Airport airfield complex reconstruction
<P class=MsoNormal style="MARGIN: 0cm 0cm 0pt; TEXT-ALIGN: justify"><SPAN lang=EN-US style="mso-ansi-language: EN-US">Ukrgosstroyekspertiza State Enterprise approved a project of Kharkiv International Airport airfield complex reconstruction (reconstruction operator is a New Systems AM Company is included into the structure of DCH Group by Aleksandr Yaroslavskyy, the investor general of preparing Kharkiv for Euro-2012). <?xml:namespace prefix = o ns = "urn:schemas-microsoft-com:office:office" /><o:p></o:p></SPAN></P> <P class=MsoNormal style="MARGIN: 0cm 0cm 0pt"><SPAN lang=EN-US style="mso-ansi-language: EN-US"><o:p> </o:p></SPAN></P> <P class=MsoNormal style="MARGIN: 0cm 0cm 0pt; TEXT-ALIGN: justify"><SPAN lang=EN-US style="mso-ansi-language: EN-US">According to the approved project, the total area of the development is 115.25 thousand sq. m; cost of construction makes 727.4 Mio UAH; the amount including the assembly works makes 474.9 Mio UAH; Equipment costs 98.7 Mio UAH; other expenses make 15.4<SPAN style="mso-spacerun: yes"> </SPAN>Mio UAH. According to the last amendment of the State Program of Preparing for Euro-2012 approved by the government, the budget appropriation devoted for the reconstruction of the airdrome complex of Kharkiv International Airport are by 14 Mio UAH less than the amount defined by Ukrgosstroyekspertiza State Enterprise at same time.<o:p></o:p></SPAN></P>