Development of a Family Vacation Hotel at 27 Zolotoy Bereg in Odessa

First Section: The basement level is 100% complete, including waterproof finishing and heat insulation

First Section:

The basement level is 100% complete, including waterproof finishing and heat insulation; laying of the first floor brick walls as well as flooring of the first floor is almost finished.

Second Section:

The basement level of the section is 100% complete, including waterproof finishing and heat insulation; laying of the first floor brick walls is beginning.

Third Section:

The construction of the basement walls is almost finished.

Fourth Section:

The pile field is prepared.

We use cookies and other technologies to remember your preferences and find out exactly how you use and interact with the site.

By using our site, you also agree to the terms of the "User Agreement" and "Regulation on the processing and protection of personal data". By clicking "I AGREE", you consent to the processing of your data.