First Section:
The basement level is 100% complete, including waterproof finishing and heat insulation; laying of the first floor brick walls as well as flooring of the first floor is almost finished.
Second Section:
The basement level of the section is 100% complete, including waterproof finishing and heat insulation; laying of the first floor brick walls is beginning.
Third Section:
The construction of the basement walls is almost finished.
Fourth Section:
The pile field is prepared.